2.1 Subsurface Exploration-Introduction

The first step in the foundation investigation is to obtain preliminary information on the project and to plan the work.
The next step is typically to perform the subsurface exploration.

The goal of the subsurface investigation is to obtain a detailed understanding of the engineering and geologic properties of the soil and rock strata and groundwater conditions that could impact the foundation.
Drill Rig used for subsurface exploration

Specific items that will be discussed in the chapter are as follows:

1.Document review (Sec. 2.2)
2.Purpose of subsurface exploration (Sec. 2.3)
3.Borings (Sec. 2.4), including a discussion of soil samplers, sample disturbance, field tests, boring
layout, and depth of subsurface exploration
4.Test pits and trenches (Sec. 2.5)
5.Preparation of logs (Sec. 2.6)
6.Geophysical techniques (Sec. 2.7)
7.Subsurface exploration for geotechnical earthquake engineering (Sec. 2.8)

8.Subsoil profile (Sec. 2.9)

1 comment:

  1. Thanks for sharing this nice post.
    while most effective the first-class screw will do. whilst and wherein to keep on piling charges with screw piles.
    We provide services of Besment waterproofing, concrete repair, footings, subsidence, basement underpin articles, basement walls, retaining walls, shoring, spray concrete, underpinning, grout injection, house underpinning(sydney), underpinning services, foundation repairs, basement garages, house restumping and ventilation sub-floor.
    screw pile sydney

    ReplyDelete